Engineer Agrees To Cover Costs For Error In Highland Avenue Project

Engineer Agrees To Cover Costs For Error In Highland Avenue Project

PIERRE — The Pierre City Commission has approved a change order on the Highland Avenue construction project. Kyle Kurth with Broz Engineering of Pierre says the change order is both typical for such a project and a bit unique…

The change order is for 106-thousand dollars and Kurth says Broz is planning to cover a cost of that because of their error…

Mayor Steve Harding says he appreciates Broz stepping up to address the error…

The change order includes an extension of the project by 18 and a half days. Kurth says contractor Morris Incorporated is making good progress on finishing Highland Avenue up.