PIERRE — City of Pierre water crews continue pushing ahead with efforts to flush the city’s water system in advance of a new drinking water treatment plant going on-line in 2022. Project Manager Gidget Palmer says two of the six zones have been completed since beginning three weeks ago…
Palmer says the process has been slower than expected…
Palmer says the flushing will continue until it is complete or it gets too cold to flush water into the streets. Even if the weather holds flushing will be suspended by Christmas and completed in the spring if not finished this fall.