PIERRE, (KCCR) — The Euclid Avenue reconstruction project is well on its way to completion. T-J Gallagher with Morris Incorporated says most of the paving is complete…
This week Fifth Street, east of Euclid will be closed with Sixth Street to follow next week. That means traffic will transition to the west side or southbound lanes of Euclid north of Fourth Street…
The final lift of asphalt on the project will be paved weather permitting October 26th which is past the October 15th seasonal limitation date for paving…
Weekly public informational meetings will continue through the completion of the project however Wednesday was the final regular media update for the project. The media will be notified of any major last minute changes.