PIERRE, (KCCR) — The Euclid Avenue reconstruction project is now only days and weeks away from completion. T-J Gallagher with Morris Incorporated says paving should be finished today…
Once the asphalt paving is finished the focus will return to concrete work…
Work crews have spent two long years working on Euclid and Gallagher says they are committed to finishing strong…
Just over a month remains until the project completion deadline of November 20th.