PIERRE, (KCCR) — Works crews are making the final push to the finish line on the Euclid Avenue Reconstruction project. T-J Gallagher with Morris Incorporated says other than sidewalks, the upper west side is complete…
Gallagher says crews are racing the weather to get the final gravel area covered in asphalt…
To make the mid-November completion deadline the Euclid project has become a seven-day-a-week endeavor…
Crossing guards will remain in place at pedestrian crossings on Euclid until traffic control signals at Euclid and Fourth Street are functional.