PIERRE, (KCCR) — Rain, while good for everyone else in drought conditions, is doing nothing to help push the Euclid Avenue reconstruction project to the finish line. T-J Gallagher says scheduled paving will have to moved back a few days…
Gallagher is hoping crews can apply a priming coat to gravel by Friday and start paving side streets by Friday as well. The prime requires three days to be in place before paving begins which puts paving on Euclid on the 29th. Traffic will still be funneled into single lanes…
With the focus shifting to final paving Gallagher says drivers and pedestrians need to be paying attention…
Gallagher says it’s frustrating to being so close to finishing the paving part of the project only to have weather delay it after a fairly good weather construction season.