PIERRE, (KCCR) — Another week of work is beginning on the Euclid Avenue reconstruction project. T-J Gallagher with Morris Incorporated says concrete work is progressing north of the west side of Euclid…
Gallagher says they would like all of the asphalt in place by October 3rd or roughly three weeks away…
Gallagher says rumble strips have been added to create more awareness for temporary stop signs in place at Fourth and Fifth Streets…
A goal for work crews is to have traffic flowing in single lanes in the north and southbound lanes by mid-October.