PIERRE, (KCCR) — On Friday, the east side of Euclid Avenue at Fourth Street was reopened to traffic. Work crews temporarily suspended sidewalk work so concrete crews could finish around the intersection. Now, Morris Incorporated Operations Manager T-J Gallagher says those crews are going back to sidewalk work…
Gallagher says pedestrian crossings will change as construction moves along…
Crews have been checking off punch list items from year one of the two year project and not much on that list remains…
Sidewalks on the east side of Euclid are installed through Seneca Avenue.