PIERRE, (KCCR) — More traffic flow changes are ahead in the near future as Euclid Avenue reconstruction crews get closer to finishing work on East Wynoka Street. T-J Gallagher with Morris Incorporated says crews are just about ready to start putting asphalt down on Wynoka…
Flaggers will be in place in the area to help direct traffic. The change will also close access to Euclid north from Broadway…
Gallagher says utility installations under Euclid have just about cleared Seneca Street…
Crews are also beginning sub-base preparations with gravel on Euclid so that paving can begin from East Wynoka to Oak Street.