PIERRE, (KCCR) — Work crews are watching the weather as close as they are the work as paving nears on the Euclid Avenue reconstruction project. T-J Gallagher with Morris Incorporated says all of the utilities have been installed and completed for the project…
The final concrete work on the west side of Euclid where Highway 1889 funnels into Pierre will be finished this week…
The second year of the project has been aided by mostly dry weather helping to keep work on track. Forecasts have pointed at over inch of rain later this week and Gallagher says its frustrating to have to fight the weather at this point in the project…
Before paving can begin over gravel a coating needs to be applied that needs three days with no rain to properly set up.