PIERRE, (KCCR) — Mild, rain-free weather hasn’t been good for much this year, but it’s been great for rebuilding Euclid Avenue. T-J Gallagher with Morris Incorporated says crews are well on their way to a goal date of October 3rd…
Gallagher says with no concrete surfacing like the south end of the project last year, crews are racing the weather to install asphalt on Euclid before they can not…
Additional signage and marking will be included before the Euclid/Broadway intersection in the southbound lanes…
The overall completion date for the Euclid reconstruction is in mid-November.