PIERRE, (KCCR) — Frequent changes are ahead on the Euclid Avenue Reconstruction project. T-J Gallagher with Morris Incorporated says pavement is starting to cover Euclid Avenue…
A utility relocation was finished sooner than expected and that means work at 4th and Euclid will see a significant change…
Both north and south traffic will be flowing with the change head-to-head in the southbound lane to 1st Street, but no turning east will be permitted on 4th Street…
Work at the 4th and Euclid intersection requiring a closure includes the final storm drain connection for the project, street light base and curb and gutter work.