PIERRE, (KCCR) — Work continues on Euclid Avenue and some connected side streets in Pierre. Josh Meintsma with Morris Incorporated says traffic has changed again on Wynoka Street…
Meintsma says water and storm drain pipe under Euclid are just about to Elizabeth Street…
Crews are also continuing to prepare for hard surface installation of asphalt for road surfaces…
The City of Pierre should be completed with infrastructure replacement under Elizabeth Street this week, then handing the area over to Morris for surface installation.