PIERRE, (KCCR) — Work crews continue making progress on utility and surface upgrades to Euclid Avenue. T-J Gallagher with prime contractor Morris Incorporated says a possible spring has slowed progress on Wynoka Street with storm sewer updates…
Gallagher expects work on Wynoka to shift to the west across Highland next week. On Euclid itself water line is nearing Oak Street….
Work is also on going on the north end of Euclid…
East Elizabeth Street is expected to close for work starting April 1st with a u-turn in place at the Elizabeth/Euclid intersection, similar to temporary u-turns used last year on the Euclid project.