PIERRE, (KCCR) — Work is off and running on the second year of the Euclid Avenue reconstruction project. T-J Gallagher with Morris Incorporated says one of the first areas to see construction is on Wynoka Street…
Gallagher says crews are already working to connect new utilities just three days into the work…
Pedestrian traffic from Wynoka to Elizabeth is prohibited with that traffic diverted one block east and west of Euclid…
Another team is working on Euclid northbound from 4th Street to the four lane divided highway. Because of that closure, the Euclid/4th Street intersection has been made a four-way stop. The intersection will remain a four-way stop even after construction as the intersection will be controlled by signals. Only one member of the public attended the public meeting with questions about Wynoka.