PIERRE, (KCCR) — Over 90 impacts delay work on the Euclid Avenue Reconstruction project in 2025 and yes, it put the project behind for the year. Morris Incorporated Operations Manager T-J Gallagher says weather was behind most of it…
Gallagher says weather accounted for a small portion of the impacts that delayed construction…
Gallagher says Morris as a company is committed to finishing the Euclid project with the best effort possible…
Department of Transportation engineers were on site every day of construction documenting each of the impacts so a reduction in penalty time can be negotiated with the prime contractor of the project.