PIERRE, (KCCR) — Euclid Avenue work crews have been battling through the impacts of nearly four inches of rain last week. Crews had hoped to be able to lay asphalt down this week from Capitol Avenue north…
Morris Incorporated Operations Manager T-J Gallagher says since they are getting later in the construction season, challenges are starting to become greater…
From Broadway Avenue south, most of that work will be done for the year by October…
A small bit of work remains north of Broadway too….
The rain is slowing work on a storm drain line to Capitol Creek…
Gallagher says one concern with the heavy rains of last week is runoff getting under curbs and gutters that have been completed and washing them out, forcing crews to not only repair dirt work but possibly the resetting and pouring of the concrete making up those parts of the work.