PIERRE, (KCCR) — Morris Incorporated work crews are looking to get a head start on the second year of the Euclid Avenue Reconstruction project this late summer and fall. Work crews returning from a project in Tripp County will be assigned to a 500 foot section of Euclid Avenue at the far north end of the project near the Donut Shoppe…
Work this week will focus on Pleasant Drive and connecting work done previously on Pierre Street and Euclid Avenue…
Another 2026 part of the project to get started this year is the Wynoka Outfall, a storm drainage connection to divert storm runoff to Capitol Creek…
Details on the Wynoka Outfall will come tomorrow during the regular Euclid Avenue Reconstruction Weekly public meeting. Those weekly meetings are open to the public and are held at 11 am at the Associated General Contractors Building across from Georgia Morse Middle School.