PIERRE, (KCCR) — Work is moving so swiftly on the Euclid Avenue reconstruction project some blocks set for 2026 may get done this year. T-J Gallagher with Morris Incorporated says they have been given the go-ahead to work at the far north end of Euclid Avenue…
This week, curb and gutter installation is expected on Capitol near the Hughes County Courthouse…
On top of getting some 2026 work done this year, Gallagher says they plan to install new Euclid drainage pipe from Wynoka Avenue to Hilger’s Gulch…
Work on Wynoka itself won’t happen until next year. Gallagher says the plan for Euclid next year is to always have some lanes open to keep traffic flowing through Pierre.