PIERRE, (KCCR) — Weather can be difficult for even meteorologists to predict. For those in the construction industry, it’s an even bigger challenge, especially for preparing roads for asphalt or concrete…
T-J Gallagher with Morris Incorporated says they have burned up all of the prescribed rain days set in to Euclid Avenue reconstruction project…
Crews have fought rain throughout the spring and summer and have worked hard to keep water out of below the base of the road…
Gallagher says once the sun comes out after a rain the base material become extremely strong. Crews also work hard to keep water from getting under concrete to prevent it from displacing.