PIERRE, (KCCR) — Pleasant Drive is expected to reopen to traffic on Friday. While some sidewalk work remains, vehicles will be able to drive across and use the tons and tons of asphalt and concrete placed on the roughly half mile of road. But, just how much was placed to make it happen…
Morris Incorporated Operations Manager T-J Gallagher says company employees and subcontractors put in over 31-thousand 700 hours of work on the first year of the Euclid project…
Hours on equipment use totaled eight-thousand hours and over 21-tons of gravel was put down below the surfacing. Over a mile-and-a-half of pipe was put into an area about a half mile long…
As for concrete, two-thousand 900 yards or 300 truck loads were put down…
All remaining work is expected to be wrapped up by mid-December.