PIERRE, (KCCR) — As the construction season nears it’s completion in a month or so work continues at full speed on the Euclid Avenue reconstruction project. Morris Incorporated Operations Manager T-J Gallagher says all work crews are pushing north past Prospect Avenue…
Gallagher says by mid-September more road surfacing will be put in place…
Walking paths on the western half of Hilger’s Gulch will be closed this week as work on the Wynoka Outfall begins. Gallagher says the walking path closures in the Gulch should be short-lived…
Work on the Wynoka Outfall will end at Wynoka Avenue and will continue in 2026. The end of 2025 work is just past the Saints Peter and Paul Catholic Church. A 500 foot section of Euclid in front of the Donut Shoppe is also expected to be completed this year.