PIERRE, (KCCR) — A half block. That’s how far work crews on the Euclid Avenue Reconstruction project are from meeting the finish line for 2025 work, but plenty of work remains. T-J Gallagher with Morris Incorporated says sanitary sewer work near the Pierre-Pleasant intersection is done for the project…
Gallagher says the next two weeks will be busy across the project…
Next week crews will begin work installing a storm drainage line from Wynoka Avenue to Capitol Creek in Hilger’s Gulch…
All of the walking trails in Hilger’s Gulch will be barricaded off west of Capitol Creek. Walking areas will remain open east of the Creek and clearly marked.