PIERRE, (KCCR) — Construction crews on the Euclid Avenue reconstruction project are working up past Prospect Avenue toward Broadway Avenue. Morris Incorporated Operations Manager T-J Gallagher says utility installers are leading the march past the Hughes County Courthouse…
The stop signs on Capitol Avenue will be in place for a few more weeks…
Gallagher says as they move through the project they find unexpected issues fairly often…
Given the positive progress crews still won’t start on 2026 portions of the project this year. Gallagher says they can not pave with asphalt after October 15th.