PIERRE, (KCCR) — Progress continues to be made in rebuilding Euclid Avenue and the utilities underneath it. T-J Gallagher with Morris Incorporated says getting Sioux Avenue reopened with utilities connected and buried leads the milestones…
Gallagher says the next two weeks will bring a busy construction site…
At that point only sidewalk installation will remain on the lowest segment of Euclid…
Communication and utility installation under Euclid will continue through Prospect Avenue with the hope of reopening Prospect toward the end of August.