PIERRE, (KCCR) — As the first phases near completion on the Euclid Avenue reconstruction plans are being finalized for the next section of work. Morris Incorporated Operations Manager T-J Gallagher says surfacing for Euclid Avenue and Pierre street are approaching…
Concrete subcontractors are also working at the Euclid/Pleasant intersection…
Utility crews have been working faster than surfacing crews which will bring the closure of Prospect Avenue earlier than expected with the reopening of Capital Avenue without traffic lights…
The next phases of the Euclid Avenue reconstruction will be Euclid from Prospect to Broadway and Pleasant from Euclid to Pierre Street.