PIERRE, (KCCR) — One final traffic pattern change is planned for Sioux Avenue before it will be open to traffic and back to normal use. Morris Incorporated Operations Manager T-J Gallagher says traffic will shift to the outside lanes in each direction…
Pierre Street, on either side of Sioux will see no immediate changes. Pedestrians will also continue using detours to Central and Highland. Pierre Street in front of the Federal Building is getting close to having a hard surface…
Euclid, in front of the Hughes County Courthouse is also nearing a hard surface installation…
The first year of the Euclid Reconstruction project will end at the St. Peter and Paul Catholic Church at Broadway. Year Two in 2026, work will go from Broadway to the start of the divided state highway. Sioux Avenue should be fully open to two-lane traffic the week of July 9th.