PIERRE, (KCCR) — Just days remain before the completion of the first phases of the Euclid Avenue reconstruction project. Heavy rain early last week forced some work to be redone on Euclid Avenue between Capitol Avenue and Pleasant Drive…
Morris Incorporated Operations Manager T-J Gallagher says crews have burned through over half of the rain days built into the first year of the project…
Both lanes of Sioux should be open in both directions after the Fourth of July, but the intersection will not be back to regular use quite yet…
Pedestrians will need to continue using detours to cross Sioux because there will be no pedestrian buttons in place at Pierre Street. Gallagher also thanked Chesterman for providing water and soft drinks to workers in care packages during hot temps last week.