PIERRE, (KCCR) — Work crews on the Euclid Avenue reconstruction are back on track. After rains in May slowed progress, Morris Incorporated Operations Manager T-J Gallagher says work continues near the Federal Building…
Gallagher says pedestrian traffic will be altered on the south side of the Federal Building…
Gallagher says work is about done on the first section of Euclid Avenue…
Work on Pleasant Drive has been completed for now and traffic has returned to normal but will be worked on later during the first year of the project. Sioux Avenue should be fully reopened by July 3rd with the first phases wrapped up by July 18th.