PIERRE, (KCCR) — Crews working on the Euclid reconstruction project put in time over the weekend to keep the project moving forward and on time. Morris Incorporated Operations Manager T-J Gallagher says the Euclid/Pleasant area will be busy with storm drain work…
Gallagher says weather doesn’t look to be a challenge for workers for awhile…
Gallagher says they are still a little behind from heavy rain a few weeks ago…
The target date for completion of the work in the current phases is July 1st. Weekly public updates on the Euclid Reconstruction are held Wednesdays at 11 am at the Associated General Contractors building across from Georgia Morse Middle School.