PIERRE, (KCCR) — Construction crews rebuilding Euclid Avenue are getting back on schedule after rain two weeks ago set them back. Morris Operations Manager T-J Gallagher says it’s been a productive week…
Those concrete crews will start work Thursday. Gallagher says in Phase 2-A, from Pleasant to Capitol Avenues, customers are using the newly installed water services…
Gallagher says noticeable changes will start to be seen by the public soon…
Gallagher says cooperation from vehicle and pedestrian traffic continues to be very good with drivers slowing down in work zones and pedestrians not walking through the construction area.